a) Scope: The project involves construction of a dredged material disposal area.

b) Impact: Will help EGENCO to meet its obligations in the MCA Dredger funded supply contract aiming at reclaiming lost generation (MWh) capacity at Kapichira Hydro Power Station.

c) Progress: The progress of the project is as detailed in the Table below:

Progress to date
  • Specifications drawn.
  • Finalized bid documents were under preparation.