a) Scope: The project involves design and construction of trash diversion at Nkula Intake.

b) Project Impact: The project will reduce impact of floating debris at Nkula thereby improving power generation.

c) Progress: The progress of the project is as detailed in the Table below:

Progress to date
  • Feasibility study, designs and tendering funded by MCC.
  • Pre-bid and site visit meeting was conducted; however, no bids were received on the day of bid opening.