wovwe

a) Scope: The project entails modernisation works for 3 generation units.

b) Project Impact: The project will improve plant reliability as well as extend its life.

c) Progress: Table below shows state of activities:

Progress to date
  • Rewound Stators for all 3 units and Rotor for unit 2.
  • Replaced MIV for all units.
  • Replaced all the 3 runners Replaced the hydraulic governor compact power unit.
  • Upgraded machine control and protection system from S5 to S7(Control system).